At the time AEMP 2008-2018 was drawn up there was no governance structure in place to oversee and coordinate the plan. AET was set up nearly three years after the launch of the plan, faced considerable resistance from conservation organizations, lacked funds for implementation and took time to establish itself. Subsequent threats to the Amboseli ecosystem, including a Nairobi Metropolitan Area on the border of the park, a public highway cutting the migration routes and a rush to develop new lodges, gave AET a central role in coordinating the responses, overseeing the Strategic Environmental Assessment and the gazettement of AEMP. The need for an integrated land use and natural resource plan pointed out in the SEA report further reinforced the role of AET. Recognizing the role of the Kajiado County in spatial planning and the communities in land use plans under the Community Land Act, AET has assumed the central role in planning and coordinating the AEMP for 2018-2028.

The revised AEMP must confront the biggest threats to the seasonal movements of pastoral livestock and wildlife, subdivision, sedentarization, and the breakdown of traditional grazing rotation causing land degradation and falling productivity of the rangelands. Alarmed by the loss of pastoral lands following the subdivision of Kimana, the area MP, MCAs and community leaders urged the group ranches to halt subdivision and look at alternatives for keeping the land open for livestock production. The rapid deterioration of pasture caused largely by a breakdown in grazing management has spurred efforts to restore governance of seasonal grazing practices, pasture productivity and livestock marketing.

A number of group ranches have begun to conduct land use plans, reestablish traditional grazing committees, rotational herding practices and establish conservancies in response to the worsening range and livestock conditions. The plans include restoring degraded lands through olopololi (grass banks), resting and rotation of pasture use, soil erosion control measures and designated wildlife conservancies. Integrated group ranch plans offer the best hope of avoiding a Kimana-like loss of pastoral lands and finding space and a place for wildlife in the pastoral rangelands.

Ogulului and Kuku have recently completed land use and grazing plans and embarked on restoration plans funded by Just Diggit. Mbirikani is in the final stages of completing its own land use and grazing plans. Selengei has embarked on similar plans and Rombo is following suit. All the group ranches in the Amboseli ecosystem have agreed to integrate and coordinate their land use, grazing and restoration plans through the Rangelands Division of AET.

By Victor N. Mose

ACP, ACC, and NAU launched a NASA-funded One Health survey using GEDI and local monitoring for ecosystem health.

By David Western, Victor N. Mose, David Maitumo, Immaculate Ombongi, Sakimba Kimiti, Winfridah Kemunto, Samuel Lekanaiya, Paul Kasaine and Sunte Kimiti

The heavy prolonged El Niño rains boosted pastures across the Amboseli ecosystem

By David Western, Immaculate Ombongi and Victor N. Mose

Our study traces the transition from traditional livestock practices based on seasonal migrations to permanent

Ecosystem planning and coordination framework

Authored by : David Western
Posted on June 28, 2018

At the time AEMP 2008-2018 was drawn up there was no governance structure in place to oversee and coordinate the plan. AET was set up nearly three years after the launch of the plan, faced considerable resistance from conservation organizations, lacked funds for implementation and took time to establish itself. Subsequent threats to the Amboseli ecosystem, including a Nairobi Metropolitan Area on the border of the park, a public highway cutting the migration routes and a rush to develop new lodges, gave AET a central role in coordinating the responses, overseeing the Strategic Environmental Assessment and the gazettement of AEMP. The need for an integrated land use and natural resource plan pointed out in the SEA report further reinforced the role of AET. Recognizing the role of the Kajiado County in spatial planning and the communities in land use plans under the Community Land Act, AET has assumed the central role in planning and coordinating the AEMP for 2018-2028.

The revised AEMP must confront the biggest threats to the seasonal movements of pastoral livestock and wildlife, subdivision, sedentarization, and the breakdown of traditional grazing rotation causing land degradation and falling productivity of the rangelands. Alarmed by the loss of pastoral lands following the subdivision of Kimana, the area MP, MCAs and community leaders urged the group ranches to halt subdivision and look at alternatives for keeping the land open for livestock production. The rapid deterioration of pasture caused largely by a breakdown in grazing management has spurred efforts to restore governance of seasonal grazing practices, pasture productivity and livestock marketing.

A number of group ranches have begun to conduct land use plans, reestablish traditional grazing committees, rotational herding practices and establish conservancies in response to the worsening range and livestock conditions. The plans include restoring degraded lands through olopololi (grass banks), resting and rotation of pasture use, soil erosion control measures and designated wildlife conservancies. Integrated group ranch plans offer the best hope of avoiding a Kimana-like loss of pastoral lands and finding space and a place for wildlife in the pastoral rangelands.

Ogulului and Kuku have recently completed land use and grazing plans and embarked on restoration plans funded by Just Diggit. Mbirikani is in the final stages of completing its own land use and grazing plans. Selengei has embarked on similar plans and Rombo is following suit. All the group ranches in the Amboseli ecosystem have agreed to integrate and coordinate their land use, grazing and restoration plans through the Rangelands Division of AET.

By David Western

At the time AEMP 2008-2018 was drawn up there was no governance structure in place to oversee and coordinate the plan. AET was set up nearly three years after the launch of the plan, faced considerable resistance from conservation organizations, lacked funds for implementation and took time to establish itself. Subsequent threats to the Amboseli ecosystem, including a Nairobi Metropolitan Area on the border of the park, a public highway cutting the migration routes and a rush to develop new lodges, gave AET a central role in coordinating the responses, overseeing the Strategic Environmental Assessment and the gazettement of AEMP. The need for an integrated land use and natural resource plan pointed out in the SEA report further reinforced the role of AET. Recognizing the role of the Kajiado County in spatial planning and the communities in land use plans under the Community Land Act, AET has assumed the central role in planning and coordinating the AEMP for 2018-2028.

The revised AEMP must confront the biggest threats to the seasonal movements of pastoral livestock and wildlife, subdivision, sedentarization, and the breakdown of traditional grazing rotation causing land degradation and falling productivity of the rangelands. Alarmed by the loss of pastoral lands following the subdivision of Kimana, the area MP, MCAs and community leaders urged the group ranches to halt subdivision and look at alternatives for keeping the land open for livestock production. The rapid deterioration of pasture caused largely by a breakdown in grazing management has spurred efforts to restore governance of seasonal grazing practices, pasture productivity and livestock marketing.

A number of group ranches have begun to conduct land use plans, reestablish traditional grazing committees, rotational herding practices and establish conservancies in response to the worsening range and livestock conditions. The plans include restoring degraded lands through olopololi (grass banks), resting and rotation of pasture use, soil erosion control measures and designated wildlife conservancies. Integrated group ranch plans offer the best hope of avoiding a Kimana-like loss of pastoral lands and finding space and a place for wildlife in the pastoral rangelands.

Ogulului and Kuku have recently completed land use and grazing plans and embarked on restoration plans funded by Just Diggit. Mbirikani is in the final stages of completing its own land use and grazing plans. Selengei has embarked on similar plans and Rombo is following suit. All the group ranches in the Amboseli ecosystem have agreed to integrate and coordinate their land use, grazing and restoration plans through the Rangelands Division of AET.

By Victor N. Mose

ACP, ACC, and NAU launched a NASA-funded One Health survey using GEDI and local monitoring for ecosystem health.

By David Western, Victor N. Mose, David Maitumo, Immaculate Ombongi, Sakimba Kimiti, Winfridah Kemunto, Samuel Lekanaiya, Paul Kasaine and Sunte Kimiti

The heavy prolonged El Niño rains boosted pastures across the Amboseli ecosystem

By David Western, Immaculate Ombongi and Victor N. Mose

Our study traces the transition from traditional livestock practices based on seasonal migrations to permanent

Posted on June 28, 2018

By David Western

At the time AEMP 2008-2018 was drawn up there was no governance structure in place to oversee and coordinate the plan. AET was set up nearly three years after the launch of the plan, faced considerable resistance from conservation organizations, lacked funds for implementation and took time to establish itself. Subsequent threats to the Amboseli ecosystem, including a Nairobi Metropolitan Area on the border of the park, a public highway cutting the migration routes and a rush to develop new lodges, gave AET a central role in coordinating the responses, overseeing the Strategic Environmental Assessment and the gazettement of AEMP. The need for an integrated land use and natural resource plan pointed out in the SEA report further reinforced the role of AET. Recognizing the role of the Kajiado County in spatial planning and the communities in land use plans under the Community Land Act, AET has assumed the central role in planning and coordinating the AEMP for 2018-2028.

The revised AEMP must confront the biggest threats to the seasonal movements of pastoral livestock and wildlife, subdivision, sedentarization, and the breakdown of traditional grazing rotation causing land degradation and falling productivity of the rangelands. Alarmed by the loss of pastoral lands following the subdivision of Kimana, the area MP, MCAs and community leaders urged the group ranches to halt subdivision and look at alternatives for keeping the land open for livestock production. The rapid deterioration of pasture caused largely by a breakdown in grazing management has spurred efforts to restore governance of seasonal grazing practices, pasture productivity and livestock marketing.

A number of group ranches have begun to conduct land use plans, reestablish traditional grazing committees, rotational herding practices and establish conservancies in response to the worsening range and livestock conditions. The plans include restoring degraded lands through olopololi (grass banks), resting and rotation of pasture use, soil erosion control measures and designated wildlife conservancies. Integrated group ranch plans offer the best hope of avoiding a Kimana-like loss of pastoral lands and finding space and a place for wildlife in the pastoral rangelands.

Ogulului and Kuku have recently completed land use and grazing plans and embarked on restoration plans funded by Just Diggit. Mbirikani is in the final stages of completing its own land use and grazing plans. Selengei has embarked on similar plans and Rombo is following suit. All the group ranches in the Amboseli ecosystem have agreed to integrate and coordinate their land use, grazing and restoration plans through the Rangelands Division of AET.

Recent Posts

By David Western, Victor N. Mose, David Maitumo, Immaculate Ombongi, Sakimba Kimiti, Winfridah Kemunto, Samuel Lekanaiya, Paul Kasaine and Sunte Kimiti

The outlook for livestock and wildlife in the short dry season normally stretching from January to the long rains

By Victor N. Mose

ACP, ACC, and NAU launched a NASA-funded One Health survey using GEDI and local monitoring for ecosystem health.

By David Western, Victor N. Mose, David Maitumo, Immaculate Ombongi, Sakimba Kimiti, Winfridah Kemunto, Samuel Lekanaiya, Paul Kasaine and Sunte Kimiti

The heavy prolonged El Niño rains boosted pastures across the Amboseli ecosystem

By David Western, Immaculate Ombongi and Victor N. Mose

Our study traces the transition from traditional livestock practices based on seasonal migrations to permanent

By Victor N. Mose, PhD, ACC/ACP, Nairobi, Kenya.

The MOSAIC field mission to the Amazon region, following a previous mission to East Africa

By Victor N. Mose, PhD, ACC/ACP, Nairobi, Kenya.

In a recent community meeting held at the Amboseli Ecosystem Trust offices in southern Kenya.

By Victor N. Mose and David Western

The Amboseli Conservation Program (ACP) has conducted regular aerial sample counts of Amboseli and eastern Kajiado

By Victor N. Mose, David Western and the ACP Team

The Amboseli Conservation Program (ACP) continued to monitor the conditions of the rangelands, livestock and wild

By Victor N. Mose

A notable discussion at the forum focused on disparities in data availability between the Global North and South.

By Victor N. Mose, David Western and the ACP Team

The effects of the good short rains have been felt in the Amboseli area.